What do building control fees cost for an extension?

For a typical house extension in England you’ll pay building control roughly £700 to £1,300 including VAT in 2026. There’s no national figure — every council sets its own scale — and it’s a completely separate charge from your planning application fee.

Get quotes for your extension

The short version

Building control is the safety check on your extension: foundations, beams, insulation, fire escape, drainage. Almost every extension needs it, including the ones that are permitted development and need no planning permission at all. The fee for that check isn’t set by central government, so it varies from one authority to the next. What stays roughly constant is the ballpark: a single-storey rear extension usually lands somewhere between £700 and £1,100 including VAT, and larger or two-storey work runs higher.

The thing worth understanding early is that the charge isn’t one payment. With a full plans application it splits in two — a plan charge when you submit your drawings, and an inspection charge when the first site visit happens. Add them together and you have the total. Choose the building notice route instead and you usually pay a single combined fee up front. Either way the money is separate from the £548 you might pay for planning, and separate again from your builder, your drawings and any structural engineer.

Building control charges for an extension, England 2026

Type of workTypical total (inc VAT)How it’s usually charged
Single-storey extension under 10m²£700–£850Plan charge on application + inspection charge at first visit
Extension or loft conversion 10–40m²£850–£1,100Plan charge + inspection charge
Extension 40–60m²£1,050–£1,300Plan charge + inspection charge
Larger or higher-value builds£1,200–£2,600+Some councils charge on the estimated cost of the work, in bands
Regularisation (work already built)from ~£400Single charge, and it’s VAT-exempt

Figures drawn from published 2025/26 local authority building control charge schedules (Folkestone & Hythe, Sussex Building Control, Havering) and cross-checked across several English councils. Charges are set by each authority under The Building (Local Authority Charges) Regulations 2010, so your council’s exact figure will differ. All include VAT at 20% except regularisation, which is VAT-exempt.

Full plans or a building notice — and why it changes the cost

There are two ways to get building control approval, and the fee is broadly similar either way. What differs is when you pay and how much risk you carry.

A full plans application means you submit drawings and the council checks them before work starts. You pay a plan charge on submission and an inspection charge later, and in return you get a formal approval you can build against — your builder is quoting on details that have already passed. A building notice lets you start sooner with no drawings checked in advance; inspectors visit as the work goes up. It suits small, simple jobs, but if an inspector disagrees with something already built, the cost of putting it right falls on you. For most extensions of any size, full plans is the calmer choice and the small extra effort pays for itself.

Council or a private inspector?

You don’t have to use your local council. Private firms can do building control too, and for a straightforward extension their quote is often close to the council’s. Since the Building Safety Act 2022 took effect — from 6 April 2024, with a short grace period to 6 July 2024 — these firms are called Registered Building Control Approvers and every one has to be registered with the Building Safety Regulator. If you’re quoted by a private inspector, it’s worth a ten-second check that they’re on the register before you sign anything.

One practical wrinkle: if a private inspector stops work for any reason and the job reverts to the council, some authorities charge a reversion fee — commonly 120% of the equivalent building notice charge, and that one isn’t subject to VAT. It’s rare, but it’s the sort of line in a fee schedule that surprises people, so it’s worth knowing it exists.

What the fee doesn’t cover

Building control checks the work; it doesn’t design it. The charge here is only the inspection fee. Your drawings, a structural engineer’s calculations for any beams or foundations, and a party wall surveyor if you’re building near a boundary are all separate and usually cost more than building control itself.

Building control is also not the same as planning permission — different process, different fee, different question. Planning asks whether you may build the thing; building control asks whether it’s built safely. See what a planning application costs for an extension, and what building control actually checks and why it matters when you sell. For the cost of the build itself — the number that dwarfs every fee on this page — there’s a full breakdown of what an extension costs by size and type on our sister site BestBuilders.

Frequently asked

For a typical single-storey extension in England, expect roughly £700 to £1,100 including VAT, rising to around £1,300 for larger extensions and more for two-storey or high-value work. There’s no national fee — each council sets its own scale — so check your local authority’s published schedule for the exact figure.
No. They’re separate approvals with separate fees. Planning permission decides whether you may build the extension; building control checks that it’s built safely, covering structure, fire, insulation and drainage. Plenty of extensions need building control but no planning application at all.
With a full plans application you pay a plan charge when you submit your drawings and an inspection charge when the first site visit takes place. Together they make up the total. A building notice usually rolls it into a single up-front fee instead.
Yes. Private firms — now called Registered Building Control Approvers — can carry out building control, and their quotes are often close to the council’s. Since April 2024 they must be registered with the Building Safety Regulator, so check they’re on the register before appointing them.
Yes, standard VAT at 20% applies to building control charges and is included in the figures here. The one exception is a regularisation charge for work already built without approval, which is VAT-exempt.
You apply to the council for a regularisation certificate. They’ll want to inspect the work — sometimes opening up finished parts to see what’s underneath — and charge a regularisation fee, typically from around £400 and VAT-exempt. It’s the route buyers’ solicitors look for when a past extension has no paperwork.
On a full plans application the plan charge is due when you submit your drawings, and the inspection charge falls due at or shortly after the first site inspection. On a building notice you generally pay the combined charge when you give notice, before work begins.

Get quotes from extension builders near you

Tell us what you’re planning and we’ll match you with up to three builders who cover your area. Free, no obligation, and you decide whether to go ahead.

Get free quotes
Written and checked by the HouseExtensionExpert editorial team · Last updated: 15 September 2026 · Charges are drawn from published 2025/26 local authority building control fee schedules and The Building (Local Authority Charges) Regulations 2010; because each authority sets its own scale, figures are indicative ranges, not quotes.Spotted something out of date? Tell us.